Post by Solution Services Corp.
590 followers
Planned shutdowns create a valuable opportunity to complete upgrades that are difficult to address during normal production. For one packaging supplier, that meant modernizing obsolete controls and drive systems within a limited shutdown window. Solution Services coordinated multiple divisions to complete PLC replacement, Ethernet communications integration, AC motor and drive installation, conduit and wiring, testing and alignment. The project demonstrates the importance of planning, communication and multi-discipline execution when downtime is limited. Read the case study: https://lnkd.in/ev6Rwitu