Post by Scan Global Logistics
126,882 followers
Each unit weighs 48 tonnes Each one is classified as dangerous goods Each one requires precision at every step The customer’s real challenge? 160 Battery Energy Storage System (BESS) containers had to leave China in 2025. But the final installation site in Hungary will not be ready until June 2026. So our solution had to do more than get the cargo from A to B. It had to protect high-value assets for months and give the customer peace of mind throughout. That’s why, alongside port handling, customs clearance, escorted night transport, and crane unloading, we’ve secured a fully insured temporary storage solution near Budapest for the five-month holding period. Here's what the customer shared: ‘𝘞𝘦 𝘩𝘢𝘷𝘦 𝘧𝘰𝘶𝘯𝘥 𝘚𝘎𝘓’𝘴 𝘵𝘦𝘢𝘮 𝘵𝘰 𝘣𝘦 𝘩𝘪𝘨𝘩𝘭𝘺 𝘱𝘳𝘰𝘧𝘦𝘴𝘴𝘪𝘰𝘯𝘢𝘭 𝘢𝘯𝘥 𝘱𝘳𝘰𝘢𝘤𝘵𝘪𝘷𝘦, 𝘢𝘯𝘥 𝘵𝘩𝘦𝘪𝘳 𝘳𝘦𝘴𝘰𝘶𝘳𝘤𝘦𝘴 𝘩𝘢𝘷𝘦 𝘣𝘦𝘦𝘯 𝘰𝘧 𝘦𝘹𝘤𝘦𝘱𝘵𝘪𝘰𝘯𝘢𝘭 𝘲𝘶𝘢𝘭𝘪𝘵𝘺. 𝘈𝘥𝘥𝘪𝘵𝘪𝘰𝘯𝘢𝘭𝘭𝘺, 𝘵𝘩𝘦 𝘱𝘢𝘳𝘵𝘯𝘦𝘳𝘴𝘩𝘪𝘱 𝘩𝘢𝘴 𝘨𝘪𝘷𝘦𝘯 𝘶𝘴 𝘨𝘳𝘦𝘢𝘵𝘦𝘳 𝘤𝘰𝘯𝘧𝘪𝘥𝘦𝘯𝘤𝘦 𝘢𝘯𝘥 𝘮𝘰𝘳𝘦 𝘰𝘱𝘵𝘪𝘰𝘯𝘴 𝘧𝘰𝘳 𝘧𝘶𝘵𝘶𝘳𝘦 𝘱𝘳𝘰𝘫𝘦𝘤𝘵𝘴.’ Stay tuned as the next phase gets underway...