Post by PERI
207,638 followers
What do standard wheel loaders π and heavy formwork have in common? They were both key to keeping the tunnel project at the E18 extension in Norway on track.Β π Β Tight geometries and extreme loads normally slow everything down. And every delay means straining a budget thatβs already tight. To prevent this, we supported the site team with a fully customised solution. π οΈ The system was assembled directly inside the tunnel and the real game changer was its mobility. The site team could move huge pre-assembled units effortlessly using just their wheel loaders. This clever setup allowed them to maintain continuous 10 metre concreting cycles seamlessly. π Need more speed? We try to save time in every step, thatβs why going from initial planning to final delivery took only 11 weeks. β±οΈ That is how the right support secures efficient workflows underground. β°οΈΒ What is your biggest bottleneck when facing tight deadlines in tunnelling? Tell us below. π PERI Norge #PERI #infrastructure #tunnel #engineering #formwork #heavyloads