Post by OX2

50,027 followers

The first wind turbine components have arrived at the Ånglarna wind farm in Dalarna, #Sweden. The 18 turbines are being supplied by Vestas, with installation being the next major milestone toward operation. Construction began in March 2024, and commissioning is planned for the end of 2026. Once operational, the wind farm is expected to generate approximately 346 GWh of renewable electricity annually, enough to power around 70,000 households. A big thank you to everyone involved in this phase of the project, including Vestas, Havator, Energy Services - Blue Water Shipping, and Felbermayr. Read more about Ånglarna: https://lnkd.in/d-7fkV6n