We are proud to share that we have successfully delivered a SinkerLine project for Van Oord. This project marks an important milestone for us, as it is the first project we have executed as the main contractor, in close collaboration with our subcontractor Lasbedrijf Wildeboer B.V. As Lapwing Partners, we took on the full project scope from the assembly stage through to final inspection and hand over stage covering the complete fabrication process. We are extremely proud of our team, who completed this project in just under 7 weeks. During this time, a 2.4 kilometer sinker pipeline was assembled, consisting of more than 200 welded pipes. A great achievement and a result we are extremely proud of! See below the end result shot by Clipz Productions Chiara Brouwer