Project Update | John Ireland Boulevard Project | St. Paul, MN On May 16, during a weekend shutdown of I-94 in St. Paul, the project team successfully completed a 1,200-yard bridge deck pour on John Ireland Boulevard. The operation was carried out safely and efficiently through strong coordination between field crews, concrete suppliers, pump operators, inspectors, and project personnel. Careful planning, clear communication, and thorough quality control measures helped maintain steady production and ensured all placement requirements were met throughout the pour. Thank you to everyone involved—great job by the entire team in making this a safe and successful effort. #KraemerNorthAmerica #kraemerNA #Kraemer #johnirelandblvd #stpaulmn #minnesota #projectupdate #constructionproject #KNA