We’re entering the final stages of a $60 million major overhaul of Unit C4 at Callide Power Station. The major program of works is more than 90 per cent complete and has involved more than 160,000 hours of work. CS Energy is delivering this overhaul under the Queensland Government's Electricity Maintenance Guarantee and the Energy Roadmap's focus on improving existing assets while building what is needed for the future. Our priority is completing this overhaul safely, on time and on budget, so that Callide C can continue to support Queensland's energy needs. CS Energy's portfolio delivered average availability of more than 95 per cent in the March quarter 2026, underscoring the value of disciplined maintenance investment. Downer