A highly motivated and energetic lead Resident Engineer working at Surbana Jurong; currently leading a team of highly experienced RTOs with diverse backgrounds supervising a mega 7-story ramp-up multi-user JTC commercial factory. Fully committed to ensuring the construction of a high-quality, high-standard, and code-compliant building that complies with the Building Control Act and Regulations. Having 10 years of experience in the construction of high-rise commercial and residential buildings in Singapore. Wilson is well adapted to the fast-paced, congested, and complex construction environment. Communication is his forte, and being able to communicate in four languages and one dialect is attributed to successful project coordination and implementation. In 2014, Wilson embarked on his journey as a project Engineer with a well-known A1 local contractor with an excellent reputation in HDB projects. With this well-structured company, he was involved with 1 executive condominium (full cycle) and 2 HDB residential projects. Wilson resigned in 2018 to join a reputable Japanese construction company to further his exposure to commercial buildings. He was introduced to the intricacies of the planning and execution of a commercial building with deep basement and a live building next to it. In this MNC company, attention to detail, prioritising planning, and a highly disciplined work ethic are instilled in him. Having gone through all the stages of construction, from site setting up to foundation works, to ERSS and deep excavation, to large poured pilecap substructures, to high-speed super-structural works, and finally handing over architectural works, Wilson will continue to immerse himself in challenging projects and partake in complex construction projects to deepen his knowledge as a civil engineer and builder.
JTC SPACE @ AMK Developer: JTC Corporation Contract Value: $287,000,000 •Lead Resident Engineer •Manage 6 C&S RTOs and 2 M&E RTOs. •Ensure that all site activities comply with the regulations and client's requirements. •Issue site memo to contractor for non-compliance an non-conformity •Full precast, prefabricated columns, beams and corewalls. •Post-tensioning system to beam & slab. •Hollow core slab, composite bondek slab & conventional FRP slab. •High Strength G85 Self Compacting Concrete •Splice Sleeve systems - N-Splice Reinforcing Bar Coupler •Structural Steelworks •Monitor all material testing and instrumentation records. •Carry out investigative works and witness NDTs •Shopdrawing checking and approvals •Checking of RFA, RFI, MOS, PE designs, Falseworks designs and approved materials.
ASCOTT LYF @ One North (CapitaLand) Contract Value: $38,000,000 •Super-Structural – Swimming pool structural works and roof canopy steel structures. •External Works –Fire engine accessway, internal drains, box culverts and linkway footing & slabs. •External Works – Removal of shotcrete wall & backfilling works. •Landscape terraces involving open-cut excavation for earth retaining structures. •Submissions –Preparation of As-builts drawings for site levels and drainage. •Witness NDT such as MPI, UT, Intumescent coating & Vermiculite thickness. •Witness NDT such as Plate load test & Nuclear density gauge test for ground compaction. •Monitoring & decommissioning of instrumentations.
Developer: TUV SUD PSB Building @ 13 International Business Park Contract Value: $61,000,000 •Foundation stage– Large Diameter Bored Pile (wet-pile condition) Witness ULT, WLT, PIT& PDA tests. •Temporary Works – Metal access decking with kingpost & metal decking. •Sheetpile works by Vibro/silent pilers/pre-bore silent pilers. •ERSS – Liaise with PE Geo with the design of ERSS & supervision, instrumentations & Annex submission •ERSS – Deep basement via strutting system using waler & main beams 3 layers - depth 11m. •ERSS – Coffer Dam - 16.5m with additional 3 layers of localized struts for the construction of a strongfloor pilecap at the basement. •ERSS – Instrumentation monitoring i.e., WSP, Inclinometer, Piezo, BM, SM, tiltmeters & VM. Provided relieve wells to mitigate pressure buildup in marine clay condition (Kallang formation). •Sub-Structural – Pilecap, basement rafter slab, retaining wall & its waterproofing system. Usage of couplers to retaining wall structures. •Super-Structural – Precast components such as PC Columns, PC N Beam, PC main beam frames. System Formworks such as Doka & Dfs. •Façade – Unitized curtain wall modules and conventional mullion & cladding panels system. •External Works – Internal drain constructions, fire engine accessway, interlocking pavers, box culvert crossings & landscape works. •Submissions – Preparation of As-builts drawings for authorities, CSC (LTA, Npark, PUB) and OMM docs
Developer: HDB Project @ Tampines Green View, TMN6C2B Contract Value: $93,411,000 •Site Setup- Construction of Main Entrance, Wash Bay, ECM holding tank, Septic tank and Workers Quarters. •Tower Crane Planning – 6 Tower cranes used for the project from foundation designs, tie backs to the dismantling of the cranes. 2 x130T Crawler Cranes •Submissions –Approval of RMCs, Crane Access, Falsework design & ERSS. •Bored Pile –Dry Pilling- Witness & recorded with RTO/RE for ULT, WLT, PDA & Rapid Load Test – Stat Rapid. Submit As-Builts. •Sub-Structural works -Completed TC Pilecaps, main building blocks & MSCP Pilecaps/ ground slabs. •Super-Structural works –MSCP structural decks, Precast planks and beams. Prefab rebar cages. •Soldier-Pile –Vibro machine to install and remove. •RC-Pilling –Execution of over 500 RC piles using just 1 rig in 2 months. •Electrical Substation –Standalone ESS from foundation to the casting of the roof. •Shophouse & Restaurant –Structural works of a 2 sty shophouses & restaurant with a green roof. •Detention Tanks -Completed 2 underground detention tanks
Developer: HDB Project @ Punggol West, PWC 32 Contract Value: $117,660,000 •RC Pilling – Familiar with Jack-In pile/ drop hammer. Setting out for pilling points- coordination’s for Linkway & Detention Tanks. PDA Test for RC Piles. •Precincts Items- Construction of linkways footing & foot path slab. Erection of Steel structures for linkways. •MSCP Archi- Coordinated the hoisting of soil & trees. -Coordinated the skimming, plastering, line painting & installation of wheel stoppers. - Completed waterproofing systems, irrigations & drainage for the roof & planters. •Submissions- Submitted Shopdrawings to Consultants for approval, Raise RFI & settle drawing discrepancies. •TOP/RI/BO Inspections – Familiar with handing over following HDB & BCA requirements.
Developer: HDB Project @ Punggol West, PWC 32 Contract Value: $ $117,660,000 •RC Pilling – Familiar with Jack-In pile/ drop hammer. Setting out for pilling points- coordination’s for Linkway & Detention Tanks. PDA Test for RC Piles. •Precincts Items- Construction of linkways footing & foot path slab. Erection of Steel structures for linkways. •MSCP Archi- Coordinated the hoisting of soil & trees. -Coordinated the skimming, plastering, line painting & installation of wheel stoppers. - Completed waterproofing systems, irrigations & drainage for the roof & planters. •Submissions- Submitted Shopdrawings to Consultants for approval, Raise RFI & settle drawing discrepancies. •TOP/RI/BO Inspections – Familiar with handing over following HDB & BCA requirements.
• Started as a part time worker and worked my way up to a full-time employee. • Appointed as assistant team leader to manage the team. • Able to work in a group environment with excellent teamwork.