Steve Sinclair

Commissioning Process Engineer

Barcelona, Catalonia, Spain

About

Experience

  • FPSO Commissioning Process Engineer at BP
    Sep 2012 - Present · 13 yrs 10 mos

    Marking of sub-system and system battery limits on Process and Utility P&ID’s. Preparation of Commissioning and Start Up Deliverable Documents. Preparation of Commissioning Function Test Procedures for Utilities and Process Systems. Coordinator and control of all Discipline Commissioning documents. Supervising Operations personnel in training and field commissioning.

  • Process and Operations Commissioning Engineer at J. Ray McDermott
    Sep 2008 - May 2011 · 2 yrs 9 mos

    Focal point for all Process / Operations interfaces with respect to the Platong Gas II facilities. Preparation of Commissioning Function Test Procedures for Utilities and Process Systems Oversight of Construction Mechanical Completions and Commissioning onsite activities Commissioning of Platong Gas II Accommodation and preparation for Gas Platform Facilities.

  • Flawless Start Up Site Coordinator at Shell EP Projects
    Oct 2007 - Sep 2008 · 1 yr

    Ensuring that the Project Team was prepared to hand over a complete and commissioned asset to SEIC which will start up and operate for its first year with no faults. Confirming that the Project Team have tested and inspected all aspects of the asset prior to Start Up. Tracking the Flawless Start-up Initiative for the areas of the Sakhalin Project. Confirming that the risk registers were complete and the construction and commissioning personnel are meeting risk mitigations. Liaising with commissioning and operations personnel to establish a preservation regime for the plant and equipment until start up

  • Commissioning Suprevisor at Shell Gabon
    Feb 2005 - Oct 2007 · 2 yrs 9 mos

    Formulated the Commissioning and Start Up Procedures for Rabi Phase 3 and Toucan Projects. Prepared the Process Operating Guides for the normal operations of the plants after Start Up. Generated the commissioning plan with sequence of events and manpower requirements. Carried out Tri-Party punch listing to confirm completion of plant and systems. Supervised the local operators in carrying out the leak testing and instrument testing. Commissioned the new Gas Injection, Produced Water Re-Injection and Produced Oil Pipelines. Witnessed the Loop Testing of all of the new Systems Commissioned and proved the correct operation of the Rabi Phase 3 systems. Preparing Work Packs for Operator Training and line marking PEFs. Carrying out “On the Job” training with the local operators