Nguyễn Văn Minh

Mining Engineer.

Vietnam

About

Experience

  • Acting Technical Service Superintendent and Technical Service Superintendent at NUI PHAO MINING COMPANY LIMITED (Masan High-Tech Material Group)
    May 2023 - May 2025 · 2 yrs 1 mo

    1 year mine Plan (MUF), Life of Mine Schedule (LOM), Budget, Pit & Dump Design, Manage Engineering team ( 9 engineer & 8 technician), Mining Contractor Management.

  • Senior Mining Engineer at NUI PHAO MINING COMPANY LIMITED ( Masan High-Tech Material group)
    Feb 2021 - Apr 2023 · 2 yrs 3 mos

    Pit Design, Dump Design, Drill and blast design by Surpac. 3 Months, Monthly, Weekly mine plan by Minesched. Manage Drill and blast contractor to blast materials to provide 10,000 tons of ore to Plant...

  • Mining ngineer at NUI PHAO MINING COMPANY LIMITED (Masan High-Tech Material group)
    Apr 2016 - Feb 2021 · 4 yrs 11 mos

    Open pit Drill and blast design, Supervised the activity of drill and blast contractor to provide 10000 tons of ore to plant, doing weekly mining plan, weekly report, monthly report about the drill and blast activity, open Pit design, dump design by Surpac.

  • Mine Planing Engineer at Bac Kan Mineral JSC
    Aug 2014 - Mar 2016 · 1 yr 8 mos

    Doing monthly mining plan, monthly report, follow with production team to catch up mining plan, control the ventilation systerm.

  • Mine Planning Engineer & Ventilation Engineer at Besra Gold Inc
    May 2012 - Jul 2014 · 2 yrs 3 mos

    Make weekly mining plan, monthly mining plan, yearly plan to archievement 1300 tons of ore per day. Underground mine design by Surpac, CAE software. Support ventilation team to calculate and set up mine ventilation system.