  • Sr. Site Superintendent at BESIX
    Sep 2024 - Present · 1 yr 10 mos

    Aramco stadium Project In charge of the structural phase as part of a team and then later on in charge of the installation of the whole stadium specific super heavy precast elements. Y Columns - raker beams and bleachers. Currently supervising the architectural side of the bowl and the pitch.

  • Construction Manager at Pairi Daiza
    Jan 2022 - Sep 2024 · 2 yrs 9 mos

    Planning and coordinating the execution of all trades for the future constuction projects of Pairi Daiza...

  • Senior Site Superintendent at PIZZAROTTI SA
    Jan 2020 - Jan 2021 · 1 yr 1 mo

    Planning and coordinating the architectural trades for the biggest hospital in Guadeloupe. Especially in charge of the joinery/door schedule (with subcontractor Malerba)/ steel work (stairs/handrails/cladding…)

  • BESIX (5 yrs 3 mos)
    • Site Superintendent
      Jan 2017 - Nov 2019 · 2 yrs 11 mos

      Civil - Infrastructure - Landscaping

    • Site Superintendent
      Jan 2016 - Jan 2017 · 1 yr 1 mo

      Assigned to the finishing department during the final stage of the project. Most precisely in charge of the balustrades and handrails scope for the entire Mall/Plaza/Leisure area.Monitor the massive production and installation of steel brackets – stainless steel brackets and posts – glass and timber from the factory to the final installation. Managed to optimize the rate of production and installation by 3 through alternative subcontractors and factories to make the final planning target realistic.

    • Site Superintendent
      Mar 2015 - Jan 2016 · 11 mos

      Dedicated to the external works and landscaping during the nine months prior the handing over of the project. Successfully managed the works of subcontractor as COLAS (worldwide leader of roads and civil engineering). Daily overviewed and supervised the works according to the landscaping architect and clients representative comments. Deeply involved in the logistic department, coordinated the planning to allow the harmonious cohabitation between landscaping and heavy façade works.

  • assistant site superintentent at Valens S.A.
    Oct 2011 - Mar 2014 · 2 yrs 6 mos

    -Assistant Site Super/Safety adviser assigned to a large scale residential project. Managing the progress of the construction through different stages -The whole structural phase: Supervised construction teams, iron workers and the general manpower. Day to day overview of the whole site focused on planning and quality, lead the weekly safety walk, ensured the implementation of safety procedure, risk analysis. Reported directly to the site superintendent. -The finishing works of 2 offices building: Successfully supervised the finishing subcontractors (drywall, electrical plumbing heating services, plaster, false ceiling, false floor, paints, cleaning), corrected the prior-delivery architect’s remarks and allowed the occupancy of the building on time. -The Façade works of the tower site: Successfully supervised the implantation and dismantling of scaffolding but also and especially of 14 masts work platforms and 3 building site lifts in collaboration with the worldwide subcontractor ALIMAK HEK. Managed the works of every façade subcontractors (nature stones, frames and windows, façade coating, balcony railing, terrace floors,...) focused on quality, planning and safety aspects. -The Wellness area : Successfully oversaw the highly detailed and specific works of the wellness area, millimeter precise implantation of the edge of an infinity pool, millimeter precise implantation and calibration of every surface with mosaic, organized the different phases of the pose of the vapor barrier envelope. Supervised all the subcontractors. Reviewed with a detail oriented mind, every architects plans and details. -Simultaneously logistic manager for the tower site : Successfully managed the crane schedule and the lift schedule. Effectively dispatched the trucks/ deliveries to avoid congestion on the streets and in the building site area. Defined storage area for every subcontractors in a really confined building site environment.